The National High Speed Rail Corporation Limited (NHSRCL) said the Overhead Equipment (OHE) system on the 50-km Surat-Bilimora section of the Mumbai-Ahmedabad bullet train corridor was energised on November 20, covering both Up and Down lines. The agency said this would pave the way for further testing along the corridor.
The corridor uses a 2x25 kV Overhead Traction System, which supplies electricity to trains through overhead wires. NHSRCL said energisation would be carried out gradually across smaller sections to ensure safety and compliance with prescribed procedures. The electrification network will have 14 Traction Substations along the 508-km route, drawing power from the National Grid.
The first traction substation at Bilimora in Gujarat's Navsari district has completed installation work in its Control Panel, Changeover Switch, Transformer and Circuit Breaker buildings. It will receive electricity from GETCO's 220 kV Ambetha Grid Substation. The elevated Surat-Bilimora section includes bridges across four rivers, a steel bridge over National Highway 53 and around 94,000 noise barriers, according to NHSRCL.
The agency urged people to stay away from overhead electrical installations and not to touch the equipment or carry out unauthorised work near it. The corridor has 12 planned stations, and the government is aiming to launch the first phase around mid-2027 between Surat and Vapi in Gujarat.