Hindustan Aeronautics Limited is facing mounting criticism over persistent delays in delivering the Light Combat Aircraft Tejas Mark 1A, with the issue drawing sharp remarks from a former Indian Air Force chief about the slow pace of aircraft integration and handover, according to a NEWS9 Live report.
The Tejas Mark 1A is central to the IAF's modernisation plan, intended to replace retiring MiG-21 squadrons. The original plan envisaged new Tejas squadrons taking the place of the phased-out MiGs, but according to NEWS9 Live, deliveries are lagging far behind retirements, raising concern over a depleting number of active fighter squadrons.
While officials acknowledge systemic problems in India's defence manufacturing, they note the delays are not solely the fault of domestic assembly lines. A key bottleneck is the Tejas's reliance on the GE F404 engine imported from the United States, described in the report as the heart of the aircraft, with deliveries repeatedly delayed. HAL's stopgap plan to build airframes and integrate engines on arrival has reportedly largely failed, as other critical imported parts also face supply disruptions.
A senior defence official acknowledged that some fault lies within the defence PSUs themselves, and the government is scrutinising HAL's internal production and assembly capabilities. Defence PSUs have been directed to review their supply chains within three months of receiving an order, and from this year timely delivery carries a weightage of 10 marks in performance assessments. The report said the episode highlights that while India has demonstrated the ability to develop advanced aviation technology, building reliable industrial-scale supply chains for mass production remains a formidable challenge.